TODAY.AZ / Business

New substation Bina to be commissioned in Feb

16 January 2006 [14:50] - TODAY.AZ
110KV substation Bina up to modern world standards will be put into exploitation in late February.

Trend reports referring to the press release spread by Azerenerji JSC.

According to Saleh Mammadov, the chief engineer, starting-up and adjustment at the substation will start soon.

The substation will allow increase of the quality and the reliability of the energy supply of the Bina settlement, as well as considerable improvement of the energy supply of the settlements Mardakan, Shuvalan, Gala and Turkan.

The substation was constructed by own forces of the energy department of the country at the initiative of MP Mehriban Aliyeva. It was equipped with modern devices, computerized and met modern energy distribution standards. Two transformers with the total capability 26MW were installed at the substation.

URL: http://www.today.az/news/business/22095.html

Print version

Views: 2452

Connect with us. Get latest news and updates.

Recommend news to friend

  • Your name:
  • Your e-mail:
  • Friend's name:
  • Friend's e-mail: